FM HAUS PLES UPDATES! Images below shows the current state of the FM Haus ples building construction, walls have been put up of the offices and for all three station studios (NauFM, YumiFM and...
FM HAUS PLES UPDATES! Images below shows the current state of the FM Haus ples building construction, walls have been put up of the offices and for all three station studios (NauFM, YumiFM and...
27th February to 1st March Progress on the new PNG FM HAUSPLES is coming along well. Ongoing wall works and cabling continues, toilets/kitchen areas within the building. Half carpark...
5th Febuary to 9th Febuary Cabling and wiring of the new building is taking place, for both upstairs and downstairs soon to install GPO's and necessary electrical components. ...
GROUND INTERIOR WALLING, PLUMBING AND IRRIGATION 15th to 19th January ...
TOP FLOOR ROOFING INSTALLATION AND GROUND FLOOR INSTALLATION 7th January to 12th January 2023 As shown in the images below, top floor roofing has already been installed along with the...
GROUND FLOOR VENTILATION PIPES IRRIGATION AND TOP FLOOR ROOFING INSTALLATIONS Jan 1st - Jan 5th construction update for FM Hausples is still undergo, with the ground floor ventilation pipes...
INTERIOR INSTALLATION AND PERLING FOR ROOFING, 18th to 22nd December Construction updates, currently doing interior installation for the whole building first floor and second floor as well....
ROOFING PERLING BEAMS 4th of December - 8th of December FM Hausples construction highlights for this week we had roofing perling beams being put up, we had our team inspect the sites and took...
FIRST FLOOR OUTER WALL 23rd - 24th of November first floor outer wall updates and Highlights shown below. So far so good in terms of the construction progress, outer walls are almost done...
FM HAUS PLES 13th - 17th First Floor Outer Walling First floor walling is still on progress and is finally taking shape. Work under the sun by the work men is paying off as the building takes it's...